Here you’l find selected news regarding the Veja Mate project.

Veja Mate - Balance of Plant: Cooperation with Siemens Energy continues
Veja Mate - Balance of Plant: Cooperation with Siemens Energy continues

In June 2022, Veja Mate and Siemens Energy signed a new Balance of Plant contract, continuing a successful cooperation project.

17 Aug 2022

2022 Consortium becomes sole shareholder of Veja Mate wind farm
2022 Consortium becomes sole shareholder of Veja Mate wind farm

In 2019, a consortium formed by Commerz Real, Ingka Group, KGAL and ALH Group bought 80% of the shares and became the major shareholder in the 402 MW Offshore Project “Veja Mate”. The consortium has recently acquired the remaining 20% of the shares from Siemens Project Ventures.

27 Jul 2022

For the second time in a row - Best Offshore Windpark 2020
For the second time in a row - Best Offshore Windpark 2020

On August 27, 2021, the Veja Mate Offshore Wind project was named “Best Offshore Wind Power Plant in Operation” for the second consecutive year. The award was presented at the 10th Offshore Economic Forum on Helgoland.

05 Oct 2021

Best Offshore Windpark 2019
Best Offshore Windpark 2019

As part of the 9th Offshore Wind Economic Forum, Veja Mate received the award for “Best Offshore Wind Power Plant in Operation”. In the overall assessment of the technical, commercial and HSE-performance criteria, the 402 MW project prevailed.

08 Aug 2020

Veja Mate receives SGS Project Certificate
Veja Mate receives SGS Project Certificate

Veja Mate is most pleased to announce the completion of its final milestone – receipt of the project certificate. Since March 2015, SGS Germany has provided Veja Mate an extensive range of quality assurance and risk assessment certification services to ensure compliance with standards of the BSH - German Maritime and Hydrographic Agency.

19 Dec 2017

Making of Veja Mate Offshore Wind Farm
Making of Veja Mate Offshore Wind Farm

View the Making of Veja Mate Offshore Wind Farm video.

08 Jul 2017

Veja Mate completes construction
Veja Mate completes construction

With the installation of the last of its 67 Siemens SWT-6.0-154 turbines last Thursday, Veja Mate completed construction in less than 14 months and just 23 months after Financial Close (FC). Commissioning activities of the last turbine was finalized today.

31 May 2017

Veja Mate reaches halfway installation milestone
Veja Mate reaches halfway installation milestone

Veja Mate Offshore Wind Farm is pleased to announce the installation of 34 of its 67 WTGs two and a half months ahead of the schedule agreed at Financial Close in July 2015.

27 Mar 2017

Veja Mate completes array cable installation
Veja Mate completes array cable installation

Veja Mate Offshore Wind Farm is most pleased to announce the completion of its array cable installation and post-lay burial activities 10 weeks ahead of schedule.

06 Feb 2017

Veja Mate delivers first power from the North Sea
Veja Mate delivers first power from the North Sea

First WTG generates renewable energy 95 kilometers from the island of Borkum

18 Jan 2017